Tuticorin Port Trust - A forward looking port
Tuticorin Port Trust - A forward looking port
Site Map             
Future Plans

DEVELOPMENT WORKS ( Status as on 30.04.2008).

I  Optimisation of Inner  Harbour                          

The Container vessels calling at Tuticorin Port are mainly feeder vessels and main- line vessels are not calling at Tuticorin Port as adequate draught is not available for such vessels. Therefore, there is a need for deepening the Harbour basin and Channel to handle vessels upto 12.80m draught (i.e. From 10.70 m to 12.80 m) to meet the future Container traffic and to attract mainline vessels. To get a draught of 12.80m, the Harbour Basin has to be dredged to a depth of (-)14.00m and the approach channel has to be dredged to a depth of (-)14.60m for a length of 4100m and the Port entrance has to be widened from 152m to 230m by removing the existing pier heads and providing additional protective spurs to maintain the tranquility conditions inside the dock basin as part of development works. 

Based on the traffic potential for Inner  Harbour Development  study report by IPA, phase wise development of Inner Harbour works has been taken up. The preparation of Techno  Economic Feasibility Report for the Inner Harbour Development mainly for  deepening of channel and harbour basin to cater 12.8m draught vessels, Construction of 9th Berth, Construction of North Cargo Berth and replacement of cargo handling equipment was entrusted to NIOT and the report was  received. A fresh application for environmental clearance was  submitted to MoE&F on 17-02-06 for approval.  MoE&F vide letter No.10-7/2005 IA III dated 9th May2006 accorded  environmental clearance for Tuticorin Port Inner Harbour Development Project at a cost of Rs.680.00 crores which includes all major projects envisaged under IHDP. The implementation  programme for  individual projects is outlined below.

The  project Construction of Berth No.9 is in progress.

1) Dredging the Dock basin and Channel to cater 12.80M draught vessels.

 The preparation of  DPR for dredging project was entrusted to M/S NIOT Chennai and the final report received.   The estimated cost  of this project is Rs.442.00 Crores.  PIB memorandum  submitted to Ministry on 10-04-06. MoE&F had accorded environmental clearance for this project on 09-05-06.Planning Commission had accorded  In -Principle approval for this project on 01-02-2007.   Ministry requested the Port to up-date the PIB and resubmit with demand for loan/grant.  The  Up-dated PIB was sent to Ministry  Vide Port's letter E(c)/F59/10/2006/ PD-I / D832 Dated  28-02-07. The clarification sought form Planning Commission has been sent to Ministry on 11th July 2007. Port approached  JBIC loan assistance under ODA loan  package for an amount of Rs.163.60 Crores  towards the cost of dredging of the channel through MoS  on 19-03-07.  Tender was  opened  on 29-06-07. No offer received. Ad directed by the Ministry Port has received the estimate cost of this Project to Rs. 538.00 Crores the final PIB submitted to Ministry on 24.12.2007. As scheduled by Ministry PIB meeting was held on 25.02.2008 . PIB Committee recommended the project for CCEA clearance. Further approval is awaited.

Port has taken up  the work dredging  the dock basin in front of  Berth 9  to cater 10.70m draught vessel at an estimated cost of Rs.40.00 Crores. Technical Bid opened on  5-12-2007 and Price bid opened on 11.01.2008.The board in its meeting held on 04.02.2008 has accorded approval for award of contract to M/S Dharti Dredging and Infrastructure, Hyderabad. Work order issued on 07.03.2008

As a part of Inner Harbour Developmental project, the work of "Conducting Mathematical model studies for widening the Port entrance" was entrusted to M/s. L&T. Ramboll.

M/s. L & T had submitted the final report on mathematical model study for widening the entrance to harbour and  made detailed presentation on 27.01.2006. The Port was not satisfied  with the report and asked  the firm to undertake further  simulation studies. The firm arranged for further real time simulation study  with their counter part M/S.  DMI, Denmark. The final study report  was furnished  during Sep.2006 and  the same  was accepted by the Port.

 In the mean time  Port approach  IIT,Chennai for Engineering Feasibility. Opinion of IIT is as follows (a)The entrance channel will be  deepened  1m extra for a length of 600m  over and above  proposed depth of dredging is enable to navigate the bigger size vessels without modifying the existing  pier head.(b)Provide two  electric  capstans of suitable capacity on both sides of the existing entrance and (c) Provide suitable rubber roller fenders in the  existing pier heads .M/S. L&T Ramboll not accept the IIT views except (a). The Marine Department /TPT also agreed M/S.L&T Ramboll suggestions. In view of the above, Port  decided to keep the existing  entrance width as same  since, the  Port is already  handling larger size vessels.

2) Construction of  Coal Berth at NBW. for NLC- TNEB ( NCB)

MoU  for the allotment of Port land for the proposed 1000MW coal based Thermal Power Plant was signed on 28-10-05 between the Port and M/S. NLC ltd. Conceptual planning of NCB was prepared by IPA. Based on the comments/suggestions of the IPA and IITM, Chennai, planning of NCB-I & NCB-II was completed.  Now, Port decided to takeup NCB-I initially for handling dusty cargoes by TPT to ease the present congestion  and subsequently NCB-II on completion of NCB-I and will be completed  before  handing  over of NCB- I to NLC.  TPT Board  in its meeting  held on   04-11-06 accorded   in-principle approval for this project ( NCB- I) at a cost of Rs.40.00Crores.  Tender opened on12-03-07.    TPT Board in its meeting  held on 06-07-07 approved the proposal to award the work to the lowest bidder M/S. Aster Teleservices Pvt. Ltd. & M/S. Tidal Marine Engg. Malaysia J.V. Chennai at a cost of Rs.40.30Crores.  Port is in  process  of  executing  a supplemental MoU  with NLC for reimbursement of the construction cost of NCB-I Vide Ports letter No. E(C) / F56/37/2004/D. 3414 Dt. 14.08.2007 formal order for allotment of land issued to NLC.   Approval of the Ministry received on 26.11.2006 to execute the work under Port's internal resources. The board in its meeting held on 04.02.2008 resolved to discharge the present L1 tender and to go for fresh tender. Estimate  under scrutiny.

3)Structural up gradation of Coal Jetty -II

Estimate for civil works  was prepared for Rs.7.95 Crores. The time schedule is 12 months.   NIT  issued on   14-11-2006.No response received to the first call. NIT for Re-tender for  this work issued on 15-03-07. Tenders opened on 25-04-07. Only one  tenderer M/S. Paresh  Construction  and Foundations Pvt. Ltd, Mumbai  submitted  his offer.  Port requested the firm   to furnish the documentary proof for work carried out  by the firm.  and the  tender committee  decided to open  the cover -II (Price Bid). Since  the tenderer had   not  extend the validity period beyond 24.09.2007. Tender committee recommends to discharge the tender. Estimate has been revised for Rs. 9.70 crores and is under technical sanction. 

4)Construction of 3 Nos. Shallow draught berths

The  estimated cost of  this project is Rs.30.00 Crores. The work will be taken up at appropriate time.

II  Construction of a Ship Building Yard at Tuticorin Port.

The Government of India, Ministry of Shipping, had developed the National Maritime Development Programmee ( NMDP) with the vision to  make India a leading player in Maritime sector  by the  year 2025. One of its  objectives is to  give a boost to shipping industry and make  India  leading ship building  nation by 2025 in world scenario. For achieving this, both  private and public participation as well as foreign direct investment would be encouraged in ship building.

MOS,RT&H set up a Committee  under the  chairmanship of Shri. R.B. Budhiraja, LAS, the then Chairman, IPA to identify the location for setting up  of two international size ship yards, one each at the east coast and the west coast of India having capacity to build and repair ships up to ULCC size.  IPA requested the Port  to provide details of locations for setting up such shipyard. The Port informed  IPA  for setting up the  shipyard at Tuticorin  and listed the reason for the same and the infrastructure available at Tuticorin The Port also informed that TPT does not  subscribe to the view that ship building  facilities should  be adequate to build ULCCs upto  300,000DWT. As the investment will be forthcoming from the private sector, this should be  left to the commercial judgement of the potential investors. Port informed the  feasibility of  developing a medium  size ship building yard in the Inner harbour of Tuticorin Port, considering the strategic location, the suitability of location of the proposed  site in terms of the natural, socio-economical and geographical conditions.

In the meantime M/S. Goodearth Maritime Ltd, Chennai came forward to prepare a pre-feasibility report by engaging international consultant M/S. Korea Maritime Consultant Company Ltd., Koreas.  Port  agreed to the proposal without any commitment to M/S. Goodearth Maritime  Ltd.  Accordingly  M/S. Korea Maritime Construction Co. Ltd. Prepared a pre-feasibility study  report and  presented  the report in a meeting held at Tuticorin Port on 08-09-06.The proposal has been  placed before the Board meeting held on 30-09-06 for seeking  in-principle approval of the TPT Board to forward the pre-feasibility  study report to Ministry  for the consideration for setting up of a ship building yard at Tuticorin.   Board accorded in principle approval for the same. Based on the Board decision, the Feasibility Study Report  has been sent to Ministry  for getting In-Principle approval vide Port's lr.No. E(c)/F48/4/PD/D.760 Dated. 21-02-07 along with memorandum for PPP Appraisal committee.

III  OUTER HARBOUR DEVELOPMENT

M/S.Consulting Engineering services, New Delhi  was entrusted to  prepare Feasibility Study report for Outer Harbour Development.   Final report received  during Feb.2007.As per the report  Port planned to takeup  phase I development of Outer Harbour at an estimated cost of Rs.4350.60 Crores.( over all)

 The memorandum of PPP appraisal committee for getting In-Principle approval for the proposal on BOT  basis

1) Construction of Breakwater, 2)Dredging and Reclamation,3) 4 Nos of Container berth   4) Providing Mechanical Equipments, Electrical, Building.  was sent to Ministry on   23-02-2007 and subsequently on 30-3-07 . Memorandum to the department of Economic affairs for Viability gap fund sent to Ministry on   17-04-07.Application  seeking environmental clearance for Outer Harbour Development  projects sent to Ministry & the Chairman TPCB, Chennai on 29-05-07. Port  approached  the JBIC for getting loan assistance on 19-03-07. The consultant appointed by the JBIC visited the Port from 17-05-07 to 24-05-07 to study the proposal. All relevant documents required by the team for the purposed of pilot study wer provided. The Meeting of Expert Committee for infrastructure development & Miscellaneous projects  of MoE&F was  held on  21-06-07 at New Mangalore to suggest the TOR for EIA for this project. The expert committee vide letter No. 10-46/2007-IA-III dated 06-07-07 suggest the additional TOR for EIA study. Budgetary offer called for  fixing agency to prepare EIA study for the Project on 24-07-07. The revised memorandum of PPPAC sent to Ministry on 22.10.2007. Budgetary offer received for the preparation of EIA study is under scrutiny. Board in its meeting held on 08.04.2008 accorded approval to  award the work "Preparation of EIA study report" to M/S National Institute of Oceanography, Goa.  Work order issued on 14.05.2008.

 


                                                                                                     Top

 

 

 


About Us | Facilities | Future Plans | What's New | Port Statistics | Chairman's Message
Daily Vessel Positions | Contact Us | Home